How to cite this paper
Xu, G., Guan, Z., Yue, L & Mumtaz, J. (2023). An efficient production planning approach based demand driven MRP under resource constraints.International Journal of Industrial Engineering Computations , 14(3), 451-466.
Refrences
Abdelhalim, A., Hamid, A., & Tiente, H. (2021). Optimisation of the Automated buffer positioning model under DDMRP logic - ScienceDirect.
Achergui, A., Allaoui, H., & Hsu, T. (2020). Strategic DDMRP's Buffer Positioning for hybrid MTO/MTS manufacturing. Paper presented at the 2020 IEEE International Conference on Technology Management, Operations and Decisions (ICTMOD).
Ali, M., & Miller, L. (2017). ERP System Implementation in Large Enterprises - A Systematic Literature Review. Journal of Enterprise Information Management, 30(4), JEIM-07-2014-0071.
Azzamouri, A., Baptiste, P., Dessevre, G., & Pellerin, R. (2021). Demand Driven Material Requirements Planning (DDMRP): A Systematic Review and Classification. Journal of Industrial Engineering and Management-Jiem, 14(3), 439-456. ://WOS:000688608600003
Benton, W. C., & Shin, H. (1998). Manufacturing planning and control: The evolution of MRP and JIT integration. European Journal of Operational Research, 110(3), 411-440.
Cheikhrouhou, N., Hachen, C., & Glardon, R. (2009). A Markovian model for the hybrid manufacturing planning and control method 'Double Speed Single Production Line'. Computers & Industrial Engineering, 57(3), 1022-1032.
Chen, J., & Peng, H. (2004). Integrated Production Management Model of MPRⅡ,JIT and TOC in Time-based Competition. Industrial engineering and management, 9(6), 75-79. ://CSCD:1661659
Glass, R., Seifermann, S., & Metternich, J. (2016, Oct 04-06). The Spread of Lean Production in the Assembly, Process and Machining Industry. Paper presented at the 5th CIRP Global Web Conference - Research and Innovation for Future Production (CIRPe), Patras, GREECE.
Godinho Filho, M., Campanini, L., & Vita, R. A. S. G. (2004). A interação MRPII - CPM: estudo de caso e proposta de um sistema híbrido. [The interaction between MRPII and CPM: a case study and a hybrid system proposal]. Production, 14(1), 31-43. ://SCIELO:S0103-65132004000100004
Kandebo, S. W. (1997). Lean initiative spurs industry transformation. Aviation Week & Space Technology, 147(4), 56-58. ://WOS:A1997YJ93300025
Kortabarria, A., Apaolaza, U., Lizarralde, A., & Amorrortu, I. (2018). Material Management without Forecasting: From MRP to Demand Driven MRP. Journal of Industrial Engineering and Management-Jiem, 11(4), 632-650. ://WOS:000456120200003
Lee, C. J., & Rim, S. C. (2019). A Mathematical Safety Stock Model for DDMRP Inventory Replenishment. Mathematical Problems in Engineering, 2019.
Luebbe, R., & Finch, B. (1992). Theory of constraints and linear programming: a comparison. International Journal of Production Research, 30(6), 1471-1478.
Miclo, R., Lauras, M., Fontanili, F., Lamothe, J., & Melnyk, S. A. (2019). Demand Driven MRP: assessment of a new approach to materials management. International Journal of Production Research, 57(1), 166-181. ://WOS:000457733000010
Ming, W. U., Xiong, S., & Shuping, Y. I. (2005). STUDY ON INTEGRATED PRODUCTION MANAGEMENT MODEL OF MRPII, JIT AND TOC. Paper presented at the Modern Industrial Engineering and Innovation in Enterprise Management vol.1.
Mirjalili, S., Mirjalili, S. M., & Lewis, A. D. (2014). Grey Wolf Optimizer. Advances in Engineering Software, 69, 46-61.
Orue, A., Lizarralde, A., & Kortabarria, A. (2020). Demand Driven MRP – The need to standardise an implementation process. International Journal of Production Management and Engineering, 8(2), 65.
Plossl, G. W. (1995). Orlicky's Material Requirements Planning. McGraw-Hill Professional.
Ptak C., S. C. (2016). Demand Driven Material Requirements Planning (DDMRP): Industrial Press, Inc.
Shofa, M. J., Moeis, A. O., & Restiana, N. (2017, Aug 29-31). Effective production planning for purchased part under long lead time and uncertain demand: MRP Vs demand-driven MRP. Paper presented at the 1st International Conference on Industrial and Systems Engineering (IConISE), Denpasar, INDONESIA.
Shofa, M. J., & Widyarto, W. O. (2017). Effective production control in an automotive industry: MRP vs. demand-driven MRP. Paper presented at the American Institute of Physics Conference Series.
Thürer, M., Fernandes, N. O., & Stevenson, M. (2020). Production planning and control in multi-stage assembly systems: an assessment of Kanban, MRP, OPT (DBR) and DDMRP by simulation. International Journal of Production Research(14), 1-15.
Watson, K. J., & Patti, A. (2008). A comparison of JIT and TOC buffering philosophies on system performance with unplanned machine downtime. International Journal of Production Research, 46(7), 1869-1885. ://WOS:000255124900008
Yu, S., & Wang, B. (2012). The application research of MRP and JIT push-pull combinative production management. Modern Manufacturing Engineering(1), 65-68. ://CSCD:4440086
Yue, L., Guan, Z., Zhang, L., Ullah, S., & Cui, Y. (2019). Multi objective lotsizing and scheduling with material constraints in flexible parallel lines using a Pareto based guided artificial bee colony algorithm. Computers & Industrial Engineering, 128(FEB.), 659-680.
Achergui, A., Allaoui, H., & Hsu, T. (2020). Strategic DDMRP's Buffer Positioning for hybrid MTO/MTS manufacturing. Paper presented at the 2020 IEEE International Conference on Technology Management, Operations and Decisions (ICTMOD).
Ali, M., & Miller, L. (2017). ERP System Implementation in Large Enterprises - A Systematic Literature Review. Journal of Enterprise Information Management, 30(4), JEIM-07-2014-0071.
Azzamouri, A., Baptiste, P., Dessevre, G., & Pellerin, R. (2021). Demand Driven Material Requirements Planning (DDMRP): A Systematic Review and Classification. Journal of Industrial Engineering and Management-Jiem, 14(3), 439-456.
Benton, W. C., & Shin, H. (1998). Manufacturing planning and control: The evolution of MRP and JIT integration. European Journal of Operational Research, 110(3), 411-440.
Cheikhrouhou, N., Hachen, C., & Glardon, R. (2009). A Markovian model for the hybrid manufacturing planning and control method 'Double Speed Single Production Line'. Computers & Industrial Engineering, 57(3), 1022-1032.
Chen, J., & Peng, H. (2004). Integrated Production Management Model of MPRⅡ,JIT and TOC in Time-based Competition. Industrial engineering and management, 9(6), 75-79.
Glass, R., Seifermann, S., & Metternich, J. (2016, Oct 04-06). The Spread of Lean Production in the Assembly, Process and Machining Industry. Paper presented at the 5th CIRP Global Web Conference - Research and Innovation for Future Production (CIRPe), Patras, GREECE.
Godinho Filho, M., Campanini, L., & Vita, R. A. S. G. (2004). A interação MRPII - CPM: estudo de caso e proposta de um sistema híbrido. [The interaction between MRPII and CPM: a case study and a hybrid system proposal]. Production, 14(1), 31-43.
Kandebo, S. W. (1997). Lean initiative spurs industry transformation. Aviation Week & Space Technology, 147(4), 56-58.
Kortabarria, A., Apaolaza, U., Lizarralde, A., & Amorrortu, I. (2018). Material Management without Forecasting: From MRP to Demand Driven MRP. Journal of Industrial Engineering and Management-Jiem, 11(4), 632-650.
Lee, C. J., & Rim, S. C. (2019). A Mathematical Safety Stock Model for DDMRP Inventory Replenishment. Mathematical Problems in Engineering, 2019.
Luebbe, R., & Finch, B. (1992). Theory of constraints and linear programming: a comparison. International Journal of Production Research, 30(6), 1471-1478.
Miclo, R., Lauras, M., Fontanili, F., Lamothe, J., & Melnyk, S. A. (2019). Demand Driven MRP: assessment of a new approach to materials management. International Journal of Production Research, 57(1), 166-181.
Ming, W. U., Xiong, S., & Shuping, Y. I. (2005). STUDY ON INTEGRATED PRODUCTION MANAGEMENT MODEL OF MRPII, JIT AND TOC. Paper presented at the Modern Industrial Engineering and Innovation in Enterprise Management vol.1.
Mirjalili, S., Mirjalili, S. M., & Lewis, A. D. (2014). Grey Wolf Optimizer. Advances in Engineering Software, 69, 46-61.
Orue, A., Lizarralde, A., & Kortabarria, A. (2020). Demand Driven MRP – The need to standardise an implementation process. International Journal of Production Management and Engineering, 8(2), 65.
Plossl, G. W. (1995). Orlicky's Material Requirements Planning. McGraw-Hill Professional.
Ptak C., S. C. (2016). Demand Driven Material Requirements Planning (DDMRP): Industrial Press, Inc.
Shofa, M. J., Moeis, A. O., & Restiana, N. (2017, Aug 29-31). Effective production planning for purchased part under long lead time and uncertain demand: MRP Vs demand-driven MRP. Paper presented at the 1st International Conference on Industrial and Systems Engineering (IConISE), Denpasar, INDONESIA.
Shofa, M. J., & Widyarto, W. O. (2017). Effective production control in an automotive industry: MRP vs. demand-driven MRP. Paper presented at the American Institute of Physics Conference Series.
Thürer, M., Fernandes, N. O., & Stevenson, M. (2020). Production planning and control in multi-stage assembly systems: an assessment of Kanban, MRP, OPT (DBR) and DDMRP by simulation. International Journal of Production Research(14), 1-15.
Watson, K. J., & Patti, A. (2008). A comparison of JIT and TOC buffering philosophies on system performance with unplanned machine downtime. International Journal of Production Research, 46(7), 1869-1885.
Yu, S., & Wang, B. (2012). The application research of MRP and JIT push-pull combinative production management. Modern Manufacturing Engineering(1), 65-68.
Yue, L., Guan, Z., Zhang, L., Ullah, S., & Cui, Y. (2019). Multi objective lotsizing and scheduling with material constraints in flexible parallel lines using a Pareto based guided artificial bee colony algorithm. Computers & Industrial Engineering, 128(FEB.), 659-680.